Calculator

Overall equipment efficiency (OEE) calculator

Fab economics and operations. Everything is calculated in your browser; nothing you enter is sent to a server.

KEY POINTS

OEE is the share of operations time spent making good wafers at the theoretical rate: availability efficiency × operational efficiency × rate efficiency × quality efficiency. Front-end fab tools often fall between about 40 and 70%. For bottleneck tools cutting standby pays off most; for cleaning and deposition tools, cutting maintenance and unscheduled downtime does.

Inputs (time categories and output for the period)

OEE (overall equipment efficiency)61.5%
Availability efficiency (uptime ratio)91.7%
Operational efficiency (productive time / uptime)84.4%
Rate efficiency80.1%
Quality efficiency99.20%
Effective throughput (per operations hour)73.8wafers/h
MTBF (productive time basis)43.3h
MTTR2.00h

The time categories are a simplified version of the SEMI E10 approach. Real fabs classify tool states automatically from the MES or tool logs and may aggregate by chamber for multi-chamber tools.

Breakdown of losses (converted to theoretical processing time)

LossTimeShare of operations time
Scheduled downtime (PM, maintenance)8.0 h4.8 %
Unscheduled downtime (failures)6.0 h3.6 %
Engineering4.0 h2.4 %
Standby (waiting for WIP or operators)20.0 h11.9 %
Speed loss (gap to theoretical throughput)25.8 h15.4 %
Quality loss (scrap, rework)0.8 h0.5 %

Where to start improving tool OEE

OEE is the share of operations time spent making good wafers at the theoretical rate. For front-end fab tools it often falls between about 40 and 70%, and the breakdown of losses varies greatly by tool type. For expensive bottleneck tools such as lithography scanners, eliminating standby comes first; for cleaning and deposition tools, cutting maintenance time and unscheduled downtime pays off.

Standby is a loss set not by the tool itself but by upstream and downstream steps, transport (AMHS) and lot release planning. Treating OEE only as a measure of a single tool's performance leads to the wrong priorities. A typical approach tracks failures separately as MTBF and MTTR and uses predictive maintenance to turn unscheduled downtime into scheduled downtime.

FAQ


What is a good OEE for fab tools?

Front-end tools typically land around 40 to 70%. The right target depends on the tool type and whether it is a bottleneck.

Is standby time the tool's fault?

Usually not. Standby comes from upstream and downstream steps, transport and lot release planning, so it should be improved at the line level.